Building Permit Requirements in Valenzuela, Metro Manila
(2025 Updated)
Last verified: December 3, 2024
Quick Summary
Estimated Fees
Contact Office of the Building Official for current fee schedule
Processing Time
3-5 weeks including clearances
Plan Sets Required
5 sets
Documentary Requirements
Check off items as you prepare them:
- Unified Application Form for Building Permit
- Lot Plan
- Homeowner's Association Clearance (where necessary)
- Transfer Certificate of Title (TCT) or Deed of Absolute Sale
- Five (5) sets of building plans signed and sealed by licensed professionals
- Bill of Materials and Cost Estimate
- Structural Analysis
- Tax Clearance
- Barangay Clearance
- Locational Clearance
- Fire Safety Evaluation Clearance (FSEC)
Required Clearances
Barangay Clearance
- Valid ID of applicant/owner
- Proof of ownership (TCT or Tax Declaration)
- Cedula
Locational Clearance
- Application form
- Barangay Clearance
- TCT or Tax Declaration copy
- Site development plan
Fire Safety Evaluation Clearance (FSEC)
- Building plans with fire safety features
- Electrical layout
Tips
- 3S Plus Valenzuela City Online Services - first and fastest integrated permit system in the country
- Online portal: online.valenzuela.gov.ph
- OBO forms downloadable from valenzuela.gov.ph/downloadableforms/pdf/obo/
- Submit original documents to OBO within 15 days to get actual permit
- Failure to submit originals within 15 days revokes provisionary permit
- Valenzuela Works portal available for permit tracking
Common Mistakes
- Not submitting original documents within 15 days
- Missing HOA clearance for subdivision properties
- Incomplete application forms
Frequently Asked Questions
Does Valenzuela have an online permit system?
Yes, Valenzuela has the 3S Plus Online Services system at online.valenzuela.gov.ph - the first and fastest integrated permit application system in the country.
How long do I have to submit original documents after online application?
You must submit original documents to the Office of the Building Official (OBO) within 15 days. Failure to do so will revoke your provisionary permit.
Download Checklist
Get a printable PDF checklist for your building permit application
Email required for download
Office Location
Valenzuela City Hall
View on Google Maps
Valenzuela City Hall, Valenzuela City, Metro Manila
Landmark: Near Valenzuela Public Market
Contact Information
Office of the Building Official (OBO), Valenzuela City Hall
Monday-Friday, 8:00 AM - 5:00 PM