Building Permit Requirements in Santa Rosa, Laguna

(2025 Updated)

Verified

Last verified: November 20, 2024

Quick Summary

Estimated Fees

₱20,000 - ₱50,000 for typical residential

Processing Time

4-6 weeks with all clearances

Plan Sets Required

5 sets

Documentary Requirements

Check off items as you prepare them:

  • Application Form (OBO Form 01)
  • Five (5) sets of architectural, structural, electrical, sanitary plans
  • Structural Analysis signed by licensed Structural Engineer
  • Bill of Materials and Detailed Cost Estimate
  • TCT or OCT (Certified True Copy)
  • Current Real Property Tax Receipt
  • Tax Clearance
  • Barangay Clearance
  • Locational Clearance from CPDO
  • Fire Safety Evaluation Clearance (BFP)
  • LLDA Clearance (if within 900m of Laguna Lake shoreline)
  • HOA Clearance (if in subdivision)

Required Clearances

Barangay Clearance

Fee: ₱100-500
Processing: 1-2 days
  • Valid ID
  • TCT/Tax Dec copy
  • Cedula

Locational Clearance

Fee: ₱800-2,500
Processing: 5-10 working days

Where: City Planning and Development Office

  • Barangay clearance
  • TCT
  • Site development plan
  • Vicinity map

FSEC

Fee: ₱1,500-5,000
Processing: 5-7 working days
  • Plans with fire safety features
  • Electrical layout

LLDA Clearance

Fee: ₱3,000-10,000
Processing: 15-30 working days

Required for properties within Laguna Lake watershed (within 900m of shoreline). Contact LLDA regional office for confirmation.

Tips

  • LLDA clearance is required for properties near Laguna Lake - confirm if your property needs it
  • Santa Rosa has stricter flood elevation requirements
  • Digital copies of plans may be requested
  • Online appointment system available

Common Mistakes

  • Forgetting LLDA clearance for properties in watershed area
  • Not following subdivision design guidelines
  • Incorrect finished floor level for flood-prone areas

Frequently Asked Questions

Do I need LLDA clearance for building in Santa Rosa?

LLDA clearance is required for properties within the Laguna Lake watershed area (approximately within 900 meters of the shoreline). Check with LLDA or the City Planning Office if your property falls within this zone.

How long does a building permit take in Santa Rosa?

Official processing is 10-15 working days, but including clearances (especially LLDA if required), expect 4-6 weeks for complete processing.

Download Checklist

Get a printable PDF checklist for your building permit application

Email required for download

Contact Information

Where:
Office of the Building Official, Santa Rosa City Hall Complex
Hours:
Monday-Friday, 8:00 AM - 5:00 PM

Special Requirements

  • LLDA Clearance Required

Need Help?

Find contractors in Santa Rosa who can handle permit processing

Find Contractors