Building Permit Requirements in Manila, Metro Manila
(2025 Updated)
Last verified: December 3, 2024
Quick Summary
Estimated Fees
₱15,000-200,000 depending on project size and location
Processing Time
2-3 months including clearances
Plan Sets Required
5 sets
Documentary Requirements
Check off items as you prepare them:
- Five (5) Sets of Location Plan with Vicinity Map (Signed & Sealed by Licensed Geodetic Engineer)
- Five (5) Copies Specification (Signed and Sealed by Architect/Civil Engineer)
- Five (5) Copies Bill of Materials (Signed and Sealed by Architect/Civil Engineer)
- Structural Computation (For Two Storey and above) signed and sealed by Civil/Structural Engineer
- Soil Analysis (For three storey and above)
- Certified True Copy of Transfer Certificate of Title (TCT) issued by Registry of Deeds
- Xerox Copy of Tax Declaration
- Xerox Copy of Tax Receipt for current year
- Barangay Clearance
- Homeowners Presidents Clearance/CRO Clearance (if applicable)
- Approved Locational Clearance Certificate issued by Planning Office
- Fire Safety Evaluation Clearance (FSEC)
Required Clearances
Barangay Clearance
Fee: ₱100-500 depending on barangay
Processing: 1-3 days
- Valid ID of applicant/owner
- Proof of ownership (TCT or Tax Declaration)
- Cedula
Locational Clearance
Fee: Contact City Planning Office for current fees
Processing: 5-10 working days
Where: City Planning Office
- Application form
- Barangay Clearance
- TCT or Tax Declaration copy
- Site development plan
Fire Safety Evaluation Clearance (FSEC)
Fee: ₱1,000-5,000 depending on project size
Processing: 3-5 working days
- Building plans with fire safety features
- Electrical layout
Tips
- Department email: depw@manila.gov.ph
- Location: Manila City Hall Bldg., A. Villegas St., Ermita, Manila 1000
- Divisions: Electrical (electrical permits), Industrial Safety (mechanical permits), Manila Building Office (building permits), Public Utilities (excavation permits)
- Soil Analysis required for 3 storey and above
- Structural Computation required for 2 storey and above
- Processing typically takes 1-2 months or longer
Common Mistakes
- Missing soil analysis for 3+ storey buildings
- Missing structural computation for 2+ storey buildings
- Not getting HOA/CRO clearance where applicable
Frequently Asked Questions
How do I contact the Department of Engineering in Manila?
Email depw@manila.gov.ph. The office is at Manila City Hall Bldg., A. Villegas St., Ermita, Manila 1000.
How long does building permit processing take in Manila?
Processing typically takes 1-2 months or longer depending on project complexity and completeness of requirements.
Download Checklist
Get a printable PDF checklist for your building permit application
Email required for download
Office Location
Manila City Hall
View on Google Maps
Manila City Hall, Manila, Metro Manila
Landmark: Near Rizal Park
Contact Information
Where:
Department of Engineering and Public Works, Manila City Hall Bldg., A. Villegas St., Ermita, Manila 1000
Department of Engineering and Public Works, Manila City Hall Bldg., A. Villegas St., Ermita, Manila 1000
Hours:
Monday-Friday, 8:00 AM - 5:00 PM
Monday-Friday, 8:00 AM - 5:00 PM