Quick Summary

Estimated Fees

₱15,000 - ₱40,000 for typical residential (100-200 sqm)

Processing Time

3-6 weeks including clearances

Plan Sets Required

5 sets

Documentary Requirements

Check off items as you prepare them:

  • Duly accomplished Application Form (BP Form No. 01)
  • Five (5) sets of plans and specifications signed and sealed by licensed professionals
  • Bill of Materials and Cost Estimate
  • Structural Analysis (for 2-storey and above)
  • Lot plan showing location of building
  • Certified True Copy of Transfer Certificate of Title (TCT) or Tax Declaration
  • Tax Clearance from City Treasurer's Office
  • Barangay Clearance
  • Locational Clearance / Zoning Certificate
  • Fire Safety Evaluation Clearance (FSEC)
  • Sanitary/Plumbing Permit
  • Electrical Permit
  • Mechanical Permit (if applicable)
  • HOA Clearance (if within subdivision)
  • DENR-EMB Environmental Compliance Certificate (for large projects)

Required Clearances

Barangay Clearance

Fee: ₱100-500 depending on barangay
Processing: 1-3 days
  • Valid ID of applicant/owner
  • Proof of ownership (TCT or Tax Declaration)
  • Two (2) passport-size photos
  • Sketch of location

Locational Clearance / Zoning Certificate

Fee: ₱500-2,000
Processing: 5-10 working days

Where: City Planning and Development Office (CPDO)

  • Application form
  • Barangay Clearance
  • Copy of TCT or Tax Declaration
  • Vicinity map
  • Site development plan

Fire Safety Evaluation Clearance (FSEC)

Fee: ₱1,000-5,000 depending on project size
Processing: 3-5 working days

Where: Bureau of Fire Protection - Bacoor Fire Station

  • Application letter
  • Building plans with fire exits and safety features indicated
  • Structural analysis (if required)
  • Electrical layout with load computation

Tips

  • Get barangay clearance first as it's required for locational clearance
  • Submit complete documents to avoid back-and-forth
  • Follow up after 10 working days if no feedback
  • Consider hiring an expediter for complex projects
  • Bring multiple copies of all documents

Common Mistakes

  • Missing signatures or seals on plans
  • Inconsistent measurements between architectural and structural plans
  • Outdated tax clearance (must be current year)
  • Wrong lot area in plans vs. title
  • Not including septic tank in sanitary plans

Frequently Asked Questions

How much does a building permit cost in Bacoor?

Building permit fees in Bacoor typically range from ₱15,000 to ₱40,000 for a standard residential building (100-200 sqm). The exact fee is calculated based on floor area and project cost.

How long does it take to get a building permit in Bacoor?

The official processing time is 15-20 working days, but realistically expect 3-6 weeks when including time to obtain clearances like barangay, locational, and fire safety clearances.

What documents do I need for a building permit in Bacoor?

Key requirements include: building plans signed by licensed professionals, lot documents (TCT or Tax Declaration), barangay clearance, locational clearance, fire safety evaluation, and various permits (electrical, sanitary, mechanical if applicable).

Do I need a locational clearance before applying for a building permit?

Yes, locational clearance (zoning certificate) from the City Planning Office is required before you can apply for a building permit in Bacoor.

Download Checklist

Get a printable PDF checklist for your building permit application

Email required for download

Contact Information

Where:
Office of the Building Official, Bacoor City Hall, Molino Blvd, Bacoor
Hours:
Monday-Friday, 8:00 AM - 5:00 PM (no noon break)

Need Help?

Find contractors in Bacoor who can handle permit processing

Find Contractors