Building Permit Requirements in Bacoor, Cavite
(2025 Updated)
Last verified: November 15, 2024
Quick Summary
Estimated Fees
₱15,000 - ₱40,000 for typical residential (100-200 sqm)
Processing Time
3-6 weeks including clearances
Plan Sets Required
5 sets
Documentary Requirements
Check off items as you prepare them:
- Duly accomplished Application Form (BP Form No. 01)
- Five (5) sets of plans and specifications signed and sealed by licensed professionals
- Bill of Materials and Cost Estimate
- Structural Analysis (for 2-storey and above)
- Lot plan showing location of building
- Certified True Copy of Transfer Certificate of Title (TCT) or Tax Declaration
- Tax Clearance from City Treasurer's Office
- Barangay Clearance
- Locational Clearance / Zoning Certificate
- Fire Safety Evaluation Clearance (FSEC)
- Sanitary/Plumbing Permit
- Electrical Permit
- Mechanical Permit (if applicable)
- HOA Clearance (if within subdivision)
- DENR-EMB Environmental Compliance Certificate (for large projects)
Required Clearances
Barangay Clearance
- Valid ID of applicant/owner
- Proof of ownership (TCT or Tax Declaration)
- Two (2) passport-size photos
- Sketch of location
Locational Clearance / Zoning Certificate
Where: City Planning and Development Office (CPDO)
- Application form
- Barangay Clearance
- Copy of TCT or Tax Declaration
- Vicinity map
- Site development plan
Fire Safety Evaluation Clearance (FSEC)
Where: Bureau of Fire Protection - Bacoor Fire Station
- Application letter
- Building plans with fire exits and safety features indicated
- Structural analysis (if required)
- Electrical layout with load computation
Tips
- Get barangay clearance first as it's required for locational clearance
- Submit complete documents to avoid back-and-forth
- Follow up after 10 working days if no feedback
- Consider hiring an expediter for complex projects
- Bring multiple copies of all documents
Common Mistakes
- Missing signatures or seals on plans
- Inconsistent measurements between architectural and structural plans
- Outdated tax clearance (must be current year)
- Wrong lot area in plans vs. title
- Not including septic tank in sanitary plans
Frequently Asked Questions
How much does a building permit cost in Bacoor?
Building permit fees in Bacoor typically range from ₱15,000 to ₱40,000 for a standard residential building (100-200 sqm). The exact fee is calculated based on floor area and project cost.
How long does it take to get a building permit in Bacoor?
The official processing time is 15-20 working days, but realistically expect 3-6 weeks when including time to obtain clearances like barangay, locational, and fire safety clearances.
What documents do I need for a building permit in Bacoor?
Key requirements include: building plans signed by licensed professionals, lot documents (TCT or Tax Declaration), barangay clearance, locational clearance, fire safety evaluation, and various permits (electrical, sanitary, mechanical if applicable).
Do I need a locational clearance before applying for a building permit?
Yes, locational clearance (zoning certificate) from the City Planning Office is required before you can apply for a building permit in Bacoor.
Download Checklist
Get a printable PDF checklist for your building permit application
Email required for download
Contact Information
Office of the Building Official, Bacoor City Hall, Molino Blvd, Bacoor
Monday-Friday, 8:00 AM - 5:00 PM (no noon break)