Building Permit Requirements in Quezon City, Metro Manila
(2025 Updated)
Last verified: December 3, 2024
Quick Summary
Estimated Fees
Based on floor area and project cost. Contact DBO for schedule.
Processing Time
2-6 weeks including clearances
Plan Sets Required
5 sets
Documentary Requirements
Check off items as you prepare them:
- Unified Application Form for Building Permit (notarized)
- Five (5) sets of building plans signed and sealed by licensed professionals
- Architectural Plans
- Structural Plans with Analysis and Computations
- Electrical Plans with Load Computation
- Plumbing/Sanitary Plans
- Mechanical Plans (if applicable)
- Electronics Plans (if applicable)
- Bill of Materials and Cost Estimate
- TCT or Tax Declaration (Certified True Copy)
- Tax Clearance
- Barangay Clearance
- Locational Clearance from CPDO
- Fire Safety Evaluation Clearance (FSEC)
- DOLE Construction Safety and Health Program (if applicable)
Required Clearances
Barangay Clearance
- Valid ID of applicant/owner
- Proof of ownership (TCT or Tax Declaration)
- Cedula
Locational Clearance
Where: City Planning and Development Office
- Application form
- Barangay Clearance
- TCT or Tax Declaration copy
- Site development plan
Fire Safety Evaluation Clearance (FSEC)
Where: Bureau of Fire Protection - Quezon City
- Building plans with fire safety features
- Electrical layout with load computation
Tips
- OIC-City Building Official: Atty. Mark Dale Diamond P. Perral
- Construction Permits Division: 8988-4242 loc. 8902
- Final Permits Division: 8988-4242 loc. 8903
- Annual Building Inspection Division: 8988-4242 loc. 8910
- Investigation and Adjudication Division: 8988-4242 loc. 8904
- Sign Board and Utilities Division: 8988-4242 loc. 8911
- Technical Compliance Evaluation Unit: 8988-4242 loc. 8909
- One Stop Shop for Construction Permits (OSSCP): 8988-4242 loc. 1401
- DBO implements National Building Code (P.D. 1096) and QC Local Building Code (SP2518, S-2016)
- Citizen's Charter documents available for 2022-2025
- QC Build Easy Handbook Volume 1 available
Common Mistakes
- Missing signatures or seals on plans
- Not scheduling appointment via kiosk machine
- Incomplete authorization letter for representatives
Frequently Asked Questions
How do I contact the Department of Building Official in Quezon City?
Call 8988-4242 and use the appropriate local extension: loc. 8912 for the City Building Official, loc. 8902 for Construction Permits, loc. 1401 for the One Stop Shop (OSSCP).
Where is the Quezon City DBO located?
The Department of the Building Official is located at Ground to 3rd Floors, Civic Center D (BRO Building), Quezon City Hall Compound.
How do I apply for a building permit in Quezon City?
Schedule an appointment via the kiosk machine at DBO Ground Floor, then submit documentary requirements on your appointment date. Present valid ID to claim the Order of Payment.
What is the processing time for building permits in Quezon City?
Processing time ranges from 3 working days (small-scale) to 20 working days (large-scale projects) depending on project complexity.
Download Checklist
Get a printable PDF checklist for your building permit application
Email required for download
Contact Information
Department of the Building Official, Ground to 3rd Floors, Civic Center D (BRO Bldg.), Quezon City Hall Compound
Monday-Friday, 8:00 AM - 5:00 PM
Special Requirements
- DOLE Safety Program Required