Building Permit Requirements in Morong, Rizal

(2025 Updated)

Verified

Last verified: December 3, 2024

Quick Summary

Estimated Fees

Contact Municipal Engineering Office for current fee schedule

Processing Time

2-4 weeks including clearances

Plan Sets Required

5 sets

Documentary Requirements

Check off items as you prepare them:

  • Five (5) complete sets of detailed plans duly signed and sealed by engineers
  • Structural design analysis (for 2+ storey buildings)
  • Boring and load test, seismic analysis, compressive strength for concrete and strength for re-bars (for 3+ storey buildings)
  • Contract of sale/lease, deed of absolute sale, or affidavit of consent (if not registered owner)
  • Bill of materials and specification signed and sealed
  • Photocopy of PRC license and PTR number of design professionals
  • Clearances from concerned agencies
  • TCT or Tax Declaration
  • Tax Clearance
  • Barangay Clearance
  • Locational Clearance
  • Fire Safety Evaluation Clearance (FSEC)

Required Clearances

Barangay Clearance

Fee: ₱100-500 depending on barangay
Processing: 1-3 days
  • Valid ID of applicant/owner
  • Proof of ownership (TCT or Tax Declaration)
  • Cedula

Locational Clearance

Fee: Contact Municipal Planning Office for current fees
Processing: 5-10 working days
  • Application form
  • Barangay Clearance
  • TCT or Tax Declaration copy
  • Site development plan

Fire Safety Evaluation Clearance (FSEC)

Fee: ₱1,000-5,000 depending on project size
Processing: 3-5 working days
  • Building plans with fire safety features
  • Electrical layout

Tips

  • Engineering Office: (02) 451-2773 local 110
  • Location: Ground Floor, New Municipal Building, San Pedro, Morong, Rizal
  • Engineering forms: morongrizal.gov.ph/download_category/engineering-forms
  • Building permit form: morongrizal.gov.ph/download/building-permit-application-form
  • Structural design analysis required for 2+ storey buildings
  • Boring test, seismic analysis required for 3+ storey buildings
  • Also handles Certificate of Annual Inspection for Business Permit

Common Mistakes

  • Missing PRC license and PTR copies of design professionals
  • Missing structural design analysis for 2+ storey buildings
  • Missing boring/seismic analysis for 3+ storey buildings
  • Missing signed bill of materials

Frequently Asked Questions

What is the contact for Morong Municipal Engineering Office?

Call (02) 451-2773 local 110. Office is on the Ground Floor, New Municipal Building, San Pedro, Morong, Rizal. Open Monday-Friday, 8am-5pm.

What special requirements does Morong have for multi-storey buildings?

For 2+ storey buildings: structural design analysis required. For 3+ storey buildings: boring and load test, seismic analysis, compressive strength for concrete, and strength for re-bars are required.

Download Checklist

Get a printable PDF checklist for your building permit application

Email required for download

Contact Information

Where:
Municipal Engineering Office, Ground Floor, New Municipal Building, San Pedro, Morong, Rizal
Hours:
Monday-Friday, 8:00 AM - 5:00 PM

Need Help?

Find contractors in Morong who can handle permit processing

Find Contractors