Building Permit Requirements in Makati, Metro Manila

(2025 Updated)

Partially Verified

Last verified: December 3, 2024

Quick Summary

Estimated Fees

Contact Engineering Dept for current fee schedule

Processing Time

1-6 weeks for residential, longer for condos

Plan Sets Required

5 sets

Documentary Requirements

Check off items as you prepare them:

  • Unified Application Form for Building Permit (notarized)
  • Five (5) sets of building plans signed and sealed by licensed professionals
  • Bill of Materials and Cost Estimate
  • Structural Analysis
  • TCT or Tax Declaration (Certified True Copy)
  • Tax Clearance
  • Barangay Clearance
  • Locational Clearance (₱3,000-6,000)
  • Fire Safety Evaluation Clearance
  • Homeowner's Association/Village Clearance (if applicable)
  • DOLE Construction Safety and Health Program

Required Clearances

Barangay Clearance to Construct

Fee: ₱300-5,000+
Processing: 1-5 days
  • Valid ID of applicant/owner
  • Proof of ownership (TCT or Tax Declaration)
  • Cedula

Locational Clearance

Fee: ₱3,000-6,000 (filing ₱100 + land use fees ₱1.20-4.10/sqm + 25% processing)
Processing: 5-15 working days

Where: Zoning Administration Unit, City Planning and Development Office

  • Application form
  • Barangay Clearance
  • Proof of property ownership
  • Business permits (if applicable)
  • Site plans

Fire Safety Evaluation Clearance (FSEC)

Fee: ₱1,000-10,000 depending on project size
Processing: 3-7 working days
  • Building plans with fire safety features
  • Electrical layout

Tips

  • Makati eBOSS online portal: makati-eboss.ph
  • Get Locational Clearance first (₱3,000-6,000) from Zoning Administration Unit, CPDO
  • Barangay Clearance to construct: ₱300-5,000+
  • HOA/Village clearance may be required for subdivision properties
  • DOLE Construction Safety and Health Program required
  • Condominium projects require ~18 permits, normally 52 weeks to process
  • Business Permit Office: 8870-1359, 8870-1362, 8870-138 (G/F City Hall Main Bldg II)

Common Mistakes

  • Not getting HOA clearance for subdivision properties
  • Forgetting DOLE Safety Program requirement
  • Incomplete locational clearance documentation

Frequently Asked Questions

Does Makati have an online permit system?

Yes, Makati has the eBOSS (Electronic Business One-Stop Shop) portal at makati-eboss.ph for various permit applications.

How long does a condominium building permit take in Makati?

Condominium projects in Makati require approximately 18 permits and normally take about 52 weeks to process completely.

How much is locational clearance in Makati?

Locational clearance costs approximately ₱3,000-6,000, including filing fee (₱100), land use fees (₱1.20-4.10 per sqm), and 25% processing fee.

Download Checklist

Get a printable PDF checklist for your building permit application

Email required for download

Contact Information

Where:
Engineering Department, Office of the Building Official, Makati City Hall
Hours:
Monday-Friday, 8:00 AM - 5:00 PM

Special Requirements

  • DOLE Safety Program Required

Need Help?

Find contractors in Makati who can handle permit processing

Find Contractors