Building Permit Requirements in Laurel, Batangas
(2025 Updated)
Last verified: December 3, 2024
Quick Summary
Estimated Fees
Contact Municipal Engineering Office for current fee schedule
Processing Time
3-5 weeks including clearances
Plan Sets Required
6 sets
Documentary Requirements
Check off items as you prepare them:
- Unified Application Form for Building Permit
- Letter consent from lot owner duly notarized (if building owner is not lot owner)
- Six (6) sets of plans, specifications, and bill of materials signed and sealed by civil engineer, electrical engineer, and sanitary engineer
- Structural analysis computation (for 2-storey buildings)
- TCT or Tax Declaration (Certified True Copy)
- Tax Clearance
- Barangay Clearance
- Locational Clearance
- Fire Safety Evaluation Clearance (FSEC)
Required Clearances
Barangay Clearance
Fee: ₱100-500 depending on barangay
Processing: 1-3 days
- Valid ID of applicant/owner
- Proof of ownership (TCT or Tax Declaration)
- Cedula
Locational Clearance
Fee: Contact Municipal Planning Office for current fees
Processing: 5-10 working days
- Application form
- Barangay Clearance
- TCT or Tax Declaration copy
- Site development plan
Fire Safety Evaluation Clearance (FSEC)
Fee: ₱1,000-5,000 depending on project size
Processing: 3-5 working days
- Building plans with fire safety features
- Electrical layout
Tips
- Main municipal number: (043) 741-4031
- Engineering Office: local extension 108
- Email: lgu@laurelbatangas.gov.ph
- Address: Poblacion, Laurel, Batangas
- Six sets of plans required (more than standard)
Common Mistakes
- Submitting only 5 sets of plans (6 required)
- Missing notarized consent from lot owner
- Missing structural analysis for 2-storey buildings
Frequently Asked Questions
How do I contact the Municipal Engineering Office in Laurel?
Call (043) 741-4031 and ask for local extension 108. Email: lgu@laurelbatangas.gov.ph.
How many sets of building plans are required in Laurel?
Laurel requires six (6) sets of plans, specifications, and bill of materials - more than the standard 5 sets required in most LGUs.
Download Checklist
Get a printable PDF checklist for your building permit application
Email required for download
Office Location
Laurel City Hall
View on Google Maps
Laurel Municipal Hall, Laurel, Batangas
Landmark: Near Taal Lake
Contact Information
Where:
Municipal Engineering Office, Municipal Hall, Poblacion, Laurel, Batangas
Municipal Engineering Office, Municipal Hall, Poblacion, Laurel, Batangas
Hours:
Monday-Friday, 8:00 AM - 5:00 PM
Monday-Friday, 8:00 AM - 5:00 PM