Building Permit Requirements in Antipolo, Rizal

(2025 Updated)

Partially Verified

Last verified: December 3, 2024

Quick Summary

Estimated Fees

Contact Department of the Building Official for current fee schedule

Processing Time

2-4 weeks including clearances

Plan Sets Required

5 sets

Documentary Requirements

Check off items as you prepare them:

  • Unified Application Form for Building Permit
  • Five (5) sets of building plans signed and sealed by licensed professionals
  • Bill of Materials and Cost Estimate
  • Structural Analysis
  • TCT or Tax Declaration (Certified True Copy)
  • Tax Clearance
  • Barangay Clearance
  • Locational Clearance
  • Fire Safety Evaluation Clearance (FSEC)

Required Clearances

Barangay Clearance

Fee: ₱100-500 depending on barangay
Processing: 1-3 days
  • Valid ID of applicant/owner
  • Proof of ownership (TCT or Tax Declaration)
  • Cedula

Locational Clearance

Fee: Contact City Planning Office for current fees
Processing: 5-10 working days
  • Application form
  • Barangay Clearance
  • TCT or Tax Declaration copy
  • Site development plan

Fire Safety Evaluation Clearance (FSEC)

Fee: ₱1,000-5,000 depending on project size
Processing: 3-5 working days
  • Building plans with fire safety features
  • Electrical layout

Tips

  • Provincial capital and largest city in Rizal with 913,712 persons (2024)
  • Main Trunkline: 689-4500
  • Address: M.L. Quezon cor. Carigma St., Brgy. San Roque, Antipolo City
  • City Engineering Office on 3rd Floor, Antipolo City Government Building
  • eBOSS portal available at eboss.antipolo.ph for business permits
  • Follow-up within 4 working days after submission recommended
  • Engineering files available at antipolo.ph/index.php/full-disclosure/engineering-files

Common Mistakes

  • Missing signatures or seals on plans
  • Incomplete application forms
  • Not following up after 4 working days

Frequently Asked Questions

What is the contact number for Antipolo City Hall?

The main trunkline is 689-4500. Ask to be connected to the Department of the Building Official for building permit inquiries.

Where is the Antipolo City Engineering Office?

The City Engineering Office is on the 3rd Floor of the Antipolo City Government Building at M.L. Quezon cor. Carigma St., Brgy. San Roque, Antipolo City.

Download Checklist

Get a printable PDF checklist for your building permit application

Email required for download

Contact Information

Where:
Department of the Building Official, 3rd Floor, Antipolo City Government Building
Contact:
689-4500
Hours:
Monday-Friday, 8:00 AM - 5:00 PM

Need Help?

Find contractors in Antipolo who can handle permit processing

Find Contractors